Mooikloof Substation Update 07 December 2021
07 December 2021
Mooikloof Substation Update
Significant progress has been made over the past 24 hours on the roofing and technical
installations at the Mooikloof sub-station.
The team finalized the steel structure of Room B yesterday afternoon and by this morning, the roof was completed and this expedited the installation of various components.
The following milestones were achieved overnight:
• 15 Switchgear (Feeder) panels installed;
• Transformer panel installed;
• Bus Coupler installed;
• Preparation of the 11kV cable re-routing completed; and
• All redundant multi-core cables have been removed from the trench.
Issued by the Communication, Marketing, and Events Department.