Mooikloof Substation Update
The progress at the Mooikloof Substation remained steady over the past 24 hours.
The targets met, since yesterday’s update, are as follows:
- The 630 sq. m transformer cables have been tested;
- The bottom and top bus-bars have been installed; these will be pressure tested by
tomorrow; - 80 % of Roof C has been completed; and
- Earthing of the sub-station was done
By tomorrow morning the team would have installed the multicores to the protection panels, demolished the gables, and finished the roofing of Room C.
Issued by the Communication, Marketing, and Events Department.